Exin Agile certification exam as a profession has an extraordinary evolution over the last few years. Exin EX0-008 exam is the forerunner in validating credentials against. Here are updated Exin EX0-008 exam questions, which will help you to test the quality features of DumpsSchool exam preparation material completely free. You can purchase the full product once you are satisfied with the product.

Question: 1

Sprint planning should result in a commitment on what will be delivered at the end of the Sprint. Who makes this commitment?

A. The Product Owner
B. The Scrum Master
C. The team

Answer: C

Question: 2

A team is estimating story points. They estimate that the story falls between a large (13) and a medium (5) and they assign a story point of 8.
What is this technique called?

A. Affinity estimation
B. Fibonacci estimation
C. Triangulation

Answer: C

Question: 3

Which Scrum ritual is meant to look back and improve upon the finished Sprint?

A. Daily Scrum.
B. Sprint Retrospective.
C. Sprint Review.

Answer: B

Question: 4

What is meant by the velocity of the team?

A. The rate a team puts in a normal work day.
B. The rate at which features are released to the customer.
C. The rate at which the team completes the work.
D. The rate at which the team renews itself.

Answer: C

Question: 5

What is a Sprint?

A. A brainstorming session in Extreme programming to generate design ideas.
B. A race between two developers to see who can complete a feature fastest.
C. One iteration in the Scrum methodology.
D. The last iteration in the Scrum project, when the team works long hours to finish the project.

Answer: C

Question: 6

What is the primary responsibility of a Scrum Master in order to keep a Scrum team working at its peak level of productivity?

A. Keeping high priority features at the top of the Product Backlog.
B. Not allowing changes to the Product Backlog once the Sprint begins.
C. Supporting the team’s decisions and resolving the team’s issues.

Answer: C